The Cardiac Surgery
Development Project (CSDP) was given the green light to proceed with construction
of both the Bergen Centre and Asper Insitute. These projects began on
March 30, 2009. Creation of administrative and medical education space
on the south end of Y3 Bergen Centre is expected to take approximately
6 to 7 months to complete.
The construction for
the space on the main, fourth and fifth floors of the Asper Institute,
the patient transport link from Asper Institute to the main hospital,
and the upgrade to the Energy Centre also began on March 30, 2009. These
other components will take approximately 18 21 months to complete.
In the coming weeks
and months there will be noise and some disruptions as the construction
proceeds. We would ask for patience and understanding during this time.
Every attempt will be made to minimize any negative impacts to work and
patient areas. To accomplish this, after hours and weekend construction
schedules will be used where possible.
|